The weekly report for the Linaro Infrastructure team may be found at:

Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-08-12
Burndown chart: 
http://people.canonical.com/~pitti/workitems/maverick/arm-infrastructure.html

Progress:

* LEP/DerivativeDistributions: Backend work under way.  User
testing of UI mockups complete.  Feedback being incorporated into
mockups for a second round of user testing.

* arm-m-private-archive-hosting-infrastructure: Changes to allow LP
archive UI to be reskinned should land soon.  Some existing bugs fixed
to allow easier testing of vostock.  Several blueprint items in review
and waiting to land.  Launchpad monthly release freeze delaying reviews
and landing slightly.

* arm-m-derived-archive-rebuild: Working together with LP team to
consider how to consolidate Linaro/LP changes.  Working on archive
deletion.  Analysis and planning complete, work about to begin on
actual coding.  Groundwork necessary is not as complete as first
thought.  Archive deletion is estimated to take longer than originally
thought

* arm-m-image-building-tool: Blueprint has one remaining work item, met
with Cody, Ian about it.  Will look into documentation changes Cody
proposed.

* arm-m-image-building-console: Progress made on getting several bugs
fixes landed.  Two of the three branches should make it into next
LexBuilder release for dogfooding by OEM.  Continuing work on other
bugs.  First security review complete, no surprises.  Started process
of choosing a new name for release.

* arm-m-automated-testing-framework: Reworking authentication code. 
Pushed a branch for doing browser startup time benchmarking.  Added
software and hardware profile gathering code.  Evaluating OpenPosix and
Phoronix test suites on ARM for correctness.  Awaiting Linaro board
approval for license.

* arm-m-validation-dashboard: JSON schema for dashboard data bundle
published.  Changes from sprint still being reviewed.  Should be landed
next week.  Initial UI work started.  Work on test tool for interacting
with test results repository coming along.  Awaiting Linaro board
approval for license. Please let me know if you have any questions.

Cheers,

Scott

-- 
Scott Bambrough <scott.bambro...@linaro.org>
Linaro Infrastructure Team Lead