Hello everybody,

Here is the timeline I plan to follow for the 17.11 release:

* Oct 27th - "Soft" feature freeze, nothing big or with high risk of
side-effects will be included into the final release if not marked as
Passed QA
* Nov 3 - "Hard" feature freeze, nothing considered as an improvement will
be pushed if not marked as Passed QA
* Nov 10 - String freeze, draft of release notes published
* Nov 17 - Only bugfixes considered as major, critical or blocker will be
pushed
* Nov 28th - Final Release

Any comments or change requests?

Regards,
Jonathan