--- Comment #2 from Andy Lavarre <alava...@gmail.com> ---
On Tue, 2019-04-02 at 06:13 +0000, Dag Andersen wrote:
> https://bugs.kde.org/show_bug.cgi?id=406127
> 
> --- Comment #1 from Dag Andersen <dand...@get2net.dk> ---
> Have you baselined your project? (Then you are not allowed to
> *delete* tasks)
> If that is not the case, is it possible for you to attach the project
> file?
> 
Dag good morning.
Thank you:
I *had* baselined it, but then added new tasksː
    After your reply I checked the     Schedule    , it said     Baselined    .
So I
    clicked     Baseline     again. A popup says "This project is baselined. Do
    you want to remove the baseline?"
    I replied yes. Then I could delete the undesired task.

    I then clicked     Calculate     and     Baseline     again, so now all is
well.

Is there an IRC channel or forum where I can get answers to questions
about Plan? I like it a lot, but (obviously) have a learning curve.
Learning by trial and error is very difficult... :-(
    For example, I've learnt that the only way to get a readable PDF
    output of Tasks is to use A0 paper size. Status requires A3 page
    size...     ɑmericans of course know very little about ɪSO. (ɪ do
    because ɪˈve spent a lot of time in ɛʊ plus am an eŋineer... ː-)

    It would be nice if it could be exported to CSV, I now use Okular
    Table Selection, but it is a bit Kludgy... Etc., etc., etc.

    Google only helps a little bit. So it would be nice to have a direct
    forum or source...

Thank you again. We can delete this bug report.
Kinnd regards, ɑndy

-- 