I am really against the notion of calling x.y.0 releases alpha/beta; it is
very confusing. If we think a release is alpha/beta quality, why not
release it as x.y.0-alpha or x.y.0-beta, and follow it up eventually with
x.y.0 GA.

I am in favor of labeling any of the newer features to be of alpha/beta
quality.

SharedCache is another close to done feature.

On Wed, Nov 11, 2015 at 12:13 PM, Vinod Vavilapalli <vino...@hortonworks.com
> wrote:

> Agreed on not mixing this with major release discussions.
>
> Okay, I just finished my review of 2.8 content.
>
> A quick summary follows.
>
> Current state of originally planned items
>
>  - Nearly Done / Done and so need to close down quickly
>     — Support *both* JDK7 and JDK8 runtimes HADOOP-11090
>     — Supporting non-exclusive node-labels: YARN-3214: Done, can push as
> an alpha / beta feature
>     — Support priorities across applications within the same queue
> YARN-1963: Can push as an alpha / beta feature
>
>  - Definitely have to move out into 2.9 and beyond
>     — Early work for disk and network isolation in YARN: YARN-2139,
> YARN-2140: Early noise, some critical pieces designed, done but not a lot
> of movement of late
>     — Classpath isolation for downstream clients HADOOP-11656: Lots of
> chatter a while ago, not much movement of late
>     — Support for Erasure Codes in HDFS HDFS-7285<
> https://issues.apache.org/jira/browse/HDFS-7285>: Moved out to 2.9 in the
> interest of stability / bake-in
>
> Non-planned features that went into 2.8.0
>
>     — The overall list of new features:
> https://issues.apache.org/jira/issues/?filter=12333994
>     — HDFS-6200 Create a separate jar for hdfs-client: Compatible
> improvement - no dimension of alpha/betaness here.
>     — HDFS-8155    Support OAuth2 in WebHDFS: Alpha / Early feature?
>     — Stability improvements ready to use:
>         — HDFS-8008    Support client-side back off when the datanodes are
> congested
>         — HDFS-8009    Signal congestion on the DataNode
>     — YARN-3611 Support Docker Containers In LinuxContainerExecutor: Well
> most of it anyways. Can push as an alpha feature.
>     — YARN-1197 Support changing resources of an allocated container: Can
> push as an alpha/beta feature
>
> Items in progress to think about in 2 weeks
>
>     — YARN Timeline Service v1.5 - YARN-4233: A short term bridge before
> YARN-2928 comes around. I think this should go in given the tremendous
> activity recently.
>     — YARN Timeline Service Next generation: YARN-2928: Lots of momentum,
> but clearly a work in progress. Two options here
>         — If it is safe to ship it into 2.8 in a disable manner, we can
> get the early code into trunk and all the way int o2.8.
>         — If it is not safe, it organically rolls over into 2.9
>     — Compatibility tools to catch backwards, forwards compatibility
> issues at patch submission, release times. Some of it is captured at
> YARN-3292. This also involves resurrecting jdiff
> (HADOOP-11776/YARN-3426/MAPREDUCE-6310) and/or investing in new tools.
>
> This is my plan of action for now in terms of the release itself
>
>  - Cut a branch about two weeks from now
>  - Do an RC mid next month (leaving ~4weeks since branch-cut)
>  - As with 2.7.x series, the first release will still be called as early /
> alpha release in the interest of
>     — gaining downstream adoption
>     — wider testing,
>     — yet reserving our right to fix any inadvertent incompatibilities
> introduced.
>
> If we can get answers on “Items to think about now” during this and next
> week, we will overall be in good shape.
>
> Thoughts?
>
> Thanks
> +Vinod
> PS:As you may have noted above, this time around, I want to do something
> that we’ve always wanted to do, but never explicitly did. I’m calling out
> readiness of each feature as they stand today so we can inform our users
> better of what they can start relying on in production clusters.
>
>
> On Oct 5, 2015, at 11:53 AM, Colin P. McCabe <cmcc...@apache.org<mailto:
> cmcc...@apache.org>> wrote:
>
> I think it makes sense to have a 2.8 release since there are a
> tremendous number of JIRAs in 2.8 that are not in 2.7.  Doing a 3.x
> release seems like something we should consider separately since it
> would not have the same compatibility guarantees as a 2.8 release.
> There's a pretty big delta between trunk and 2.8 as well.
>
> cheers,
> Colin
>
> On Sat, Sep 26, 2015 at 1:36 PM, Chris Douglas <cdoug...@apache.org
> <mailto:cdoug...@apache.org>> wrote:
> With two active sustaining branches (2.6, 2.7), what would you think
> of releasing trunk as 3.x instead of pushing 2.8? There are many new
> features (EC, Y1197, etc.), and trunk could be the source of several
> alpha/beta releases before we fork the 3.x line. -C
>
> On Sat, Sep 26, 2015 at 12:49 PM, Vinod Vavilapalli
> <vino...@hortonworks.com<mailto:vino...@hortonworks.com>> wrote:
> As you may have noted, 2.8.0 got completely derailed what with 2.7.x and
> the unusually long 2.6.1 release.
>
> With 2.6.1 out of the way, and two parallel threads in progress for 2.6.2
> and 2.7.2, it’s time for us to look back at where we are with Hadoop 2.8.
>
> I’ll do a quick survey of where the individual features are and the amount
> of content already present in 2.8 and kick-start 2.8.0 process again.
>
> +Vinod
>
>
> On Apr 21, 2015, at 2:39 PM, vino...@apache.org<mailto:vino...@apache.org>
> wrote:
>
> With 2.7.0 out of the way, and with more maintenance releases to stabilize
> it, I propose we start thinking about 2.8.0.
>
> Here's my first cut of the proposal, will update the Roadmap wiki.
> - Support *both* JDK7 and JDK8 runtimes: HADOOP-11090
> - Compatibility tools to catch backwards, forwards compatibility issues at
> patch submission, release times. Some of it is captured at YARN-3292. This
> also involves resurrecting jdiff (HADOOP-11776/YARN-3426/MAPREDUCE-6310)
> and/or investing in new tools.
> - HADOOP-11656 Classpath isolation for downstream clients
> - Support for Erasure Codes in HDFS HDFS-7285
> - Early work for disk and network isolation in YARN: YARN-2139, YARN-2140
> - YARN Timeline Service Next generation: YARN-2928. At least branch-merge
> + early peek.
> - Supporting non-exclusive node-labels: YARN-3214
>
> I'm experimenting with more agile 2.7.x releases and would like to
> continue the same by volunteering as the RM for 2.8.x too.
>
> Given the long time we took with 2.7.0, the timeline I am looking at is
> 8-12 weeks. We can pick as many features as they finish along and make a
> more predictable releases instead of holding up releases for ever.
>
> Thoughts?
>
> Thanks
> +Vinod
>
>
>
>