Hi,

The podling reports this month [1] seem pretty good in general.

I spent some time unifying report formatting and fixing some minor
issues (like Stanbol needing an intro paragraph). I also pinged
NPanday and Zeta Components that have still not reported (both also
missed their previous report), asking them to report again next month
unless they already have something ready. HISE didn't report as the
project is just about to retire.

Based on the submitted reports I'd divide the projects into the
following three rough categories:

1) Still getting started at the Incubator (7 podlings)
   - Any23
   - Bloodhound
   - Cordova
   - DeltaSpike
   - DeviceMap
   - Flex
   - Openmeetings

2) Not yet ready to graduate, categorized by most pressing issue (12 podlings)
   2a) IP clearance: Amber
   2b) Release trouble: Clerezza, Stanbol
   2c) Low activity: Ambari, Nuvem, PhotArk, SIS, Wink
   2d) Low diversity: Airavata, Droids, VCL, Wookie

3) Ready to graduate (3 podlings)
   - Jena
   - Lucene.NET
   - OpenNLP

Also, I looked at the number of mentors signing off a report. Most had
at least two explicit sign-offs, which is pretty good. Here's the list
of projects with less than that:

- no signoffs: Amber, OpenNLP
- one signoff: Any23, Ambari, Jena, Lucene.NET, Nuvem, Openmeetings,
PhotArk, Wink

I'm not yet sure how useful (or even meaningful) summaries like this
are. If people find this summary useful or more importantly something
we can act on, then we could try doing it again for future reports.

[1] http://wiki.apache.org/incubator/February2012

BR,

Jukka Zitting

---------------------------------------------------------------------