Alex, same answer as for March 2011 report:

Celix is listed in the Monthly section of ReportingSchedule.
Clutch gathers that data.

If your project feels that it has finished their monthly
reporting cycles, then edit that schedule to go onto quarterly.
It is all in your control from here on in.

You can report more often if you want.

See the notes to projects at the top of ReportingSchedule.

-David

Noel J. Bergman wrote:
> Alex,
>
> > Celix is due in July according to
> > http://wiki.apache.org/incubator/ReportingSchedule
>
> > Is the automated system supposed to email every month? Or does it
> > follow the schedule and is there something wrong?
>
> I was going by what was on the May Wiki page.  I just checked the reporting
> schedule, and also the April report, and see that Celix did report in April,
> as scheduled.
>
>       --- Noel

---------------------------------------------------------------------
To unsubscribe, e-mail: general-unsubscr...@incubator.apache.org
For additional commands, e-mail: general-h...@incubator.apache.org

Reply via email to