John Hendy <jw.he...@gmail.com> writes:

> I think I've narrowed this down to two things:
> 1) org-taskjuggler-get-start (and probably *-get-end) is not working properly
> 2) project applicable keywords stored in property drawer should be
> being parsed, but they're not
>
>
> That's about all I'm good for with my current elisp knowledge!

Did you try to set a schedule for the task at the root of the project
(with C-c C-s)?

`org-taskjuggler-get-start' expects a SCHEDULED: <...> line below the
headline.


Regards,

-- 
Nicolas Goaziou