On 02/04/2012 11:45 PM, Brian van den Broek wrote:
On 4 Feb 2012 22:55, "Simon Thum"<simon.t...@gmx.de> wrote:
Hi all,
it seems to me that specifying recurring multi-days things like
<2012-12-24 +1y>--<2012-12-15> do not show up in the agenda. I know there
sexp dates, but these have other drawbacks.
I've not tried such things, but if that is your actual example, your start
date is for a date after your end date. That can't be helping :-)
Well, I meant <2012-12-24 +1y>--<2012-12-25> but I didn't get it to work
nonetheless ;(
Cheers,
Simon