Dnia 09.02.2018 Michael Welle <mwe012...@gmx.net> napisaĆ/a: > Hello, > > Piotr Isajew <p...@ex.com.pl> writes: > >> Hi, >> >> I wonder if it's possible to have something like a clocktable, but >> based on effort, not the clocked time. My use case is that at the >> beginning of the project, when the effort for each of tasks is >> estimated, but none has been worked on yet, I need to generate >> some reports (preferably with tag filters) to show the aggregated >> effort for parts of the project. > does this stripped-down example help? [..] > * Effort > #+BEGIN: columnview :hlines 2 :id "756fcb74-2e46-4757-82b8-461ed30a5f11"
Yes, it does. I still have to solve the issue of setting tag filters, but you helped a lot. Thank you :)