Hi all,

I’ve just branched v9.0.x, roughly 2 months behind schedule. It’s critical that 
for the next few months, all PRs merged to master which are critical for v9.0.0 
release, gets a Project of v9.0.x. All milestones on master commits should now 
be v10.0.0, if a PR gets accepted to v9.0.x, we will change the milestone 
accordingly after cherry-picking.

I’ve moved all v9.0.0 Milestone PRs and Issues to v10.0.0. We need to examine 
the ones marked for v9.1.0 more carefully, many of them are very old. Again, 
all new master commits are now for v10.0.0, and you must make a case for such 
commits to be cherry-picked to v9.0.0 via the v9.0.x Project tab.

Cheers,,

— leif