I would prefer that this regression get resolved before we announce
the 10.0 release candidate:
https://github.com/apache/incubator-nuttx/issues/1804

Thanks
Xiang

On Fri, Sep 25, 2020 at 12:34 AM Adam Feuer <a...@starcat.io> wrote:
>
> Alin,
>
> Thanks, I would love your help on the next release, I'm looking forward to
> working together.
>
> cheers
> adam
>
>
> On Wed, Sep 23, 2020 at 11:15 PM Jerpelea, Alin <alin.jerpe...@sony.com>
> wrote:
>
> > HI Brennan,
> >
> > The release schedule looks god.
> >
> > @Adam Feuer
> > I want to help you on the next release process if you want
> >
> > Regards
> > Alin
> >
> >
> > -----Original Message-----
> > From: Adam Feuer <a...@starcat.io>
> > Sent: den 23 september 2020 21:13
> > To: dev@nuttx.apache.org
> > Subject: Re: [DISCUSS] NuttX 10.0.0 Release schedule
> >
> > Brennan,
> >
> > Thanks for doing all this. I'm willing to be release manager for the next
> > release after 10.0.0.
> >
> > -adam
> >
> >
> > On Tue, Sep 22, 2020 at 10:13 PM Brennan Ashton <bash...@brennanashton.com
> > >
> > wrote:
> >
> > > Hey all, we have talked in loose terms about this release, but I think
> > > it is time we committed, it has been probably too long since our last
> > > release.
> > >
> > > Here is what I would propose for a release schedule:
> > >
> > >   09/28/20 -- Master Stability Window (keep the merging of risky PRs
> > > to a minimum this week)
> > >   10/03/20 -- Create the 10.0 release branch
> > >   10/04/20 - 10/12/20 -- Stabilize / test / release notes
> > >      Additionally in this window we need to make a couple CI tweeks to
> > > handle the new docs off of the release branch (I expect this won't be
> > > much work, but will be easier with the branch in place)
> > >   10/12/20 -- Tag RC0 and call for PPMC / Community Vote
> > >   10/15/20 (or when we have the votes) Call for IPMC Vote  or create a
> > > new RC if needed to address issues
> > >   10/23/20 (Pending votes and RC0 issues) --  Release RC0
> > >   10/24/20 -- Update site and announce (we have to wait for download
> > > mirrors to sync).
> > >
> > > I know that is almost a month, but that is usually about how long it
> > > takes for the whole process, but realistically there is only a week or
> > > so where we are aiming to slow down and stabilize the master branch.
> > > The rest of it is testing, documenting, voting, and waiting time.
> > >
> > > I can be the release manager again for this one. But it would be great
> > > if someone else jumps in for the release after and I will try to
> > > document things a bit more to make the process easier.  We will need
> > > to have more than one release manage to graduate, there are other
> > > projects that have run into this.
> > >
> > > --Brennan
> > >
> >
> >
> > --
> > Adam Feuer <a...@starcat.io>
> >
>
>
> --
> Adam Feuer <a...@starcat.io>

Reply via email to