Hi Igniters!

I've filled an umbrella ticket [1] to track all tickets which will be
implemented in phase 1.
We reworked internals completely that allow us to provide us with
several main features:
* synchronous deployment
* propagation of deployment errors across the cluster
* basic deployment failure policies
* processing pending requests in case of coordinator change
* etc.

The solution will be ready for review, at best, 30 of September.

If code freeze will be at the end of September, then we have no time
to do a review.

Are we sure that we don't have other tasks which will be included in
2.7 and may move the code freeze date?

[1] https://issues.apache.org/jira/browse/IGNITE-9607


On Wed, Sep 19, 2018 at 1:14 PM Anton Vinogradov <a...@apache.org> wrote:
>
> Nikolay,
>
> I'll perform prereview once PR will be ready.
> Then we'll need some time to fix all found issues.
> After that final review by another expert will be required.
>
> Let's define the deadline for final PR and reviewer (Alexey Goncharuk?).
> In other words, let's define the exact date until which final PR should be 
> provided to have chances to become a part of 2.7.
>
>
> ср, 19 сент. 2018 г. в 12:46, Nikolay Izhikov <nizhi...@apache.org>:
>>
>> Hello, Igniters.
>>
>> Currently, we are working on release scope for Apache Ignite 2.7
>> We had plans to include "Service Grid Redesign. Phase 1" to 2.7 release.
>>
>> If I understand correctly, the plan is following - We should have PR that
>> is ready for review at the end of September.
>>
>> This deadline is very close to the code freeze date.
>>
>> Let's discuss, how we should handle this risks?
>> Who will be able to review this PR when it's will be ready?
>> Vyacheslav, can you comment on this?



--
Best Regards, Vyacheslav D.