Hi Devs! Based on the previously agreed release schedule for the operator <https://cwiki.apache.org/confluence/display/FLINK/Release+Schedule+and+Planning> the next target release date is Aug 1. According to the schedule July 11 would have been Feature Freeze and Jul 18 the time of release cut.
I propose the following timeline based on the current status: Feature Freeze: July 13 (tomorrow) Release Branch Cut + RC1: July 20 Based on this we would not merge new feature PRs opened after tomorrow before the 1.1 release is cut. There are a few outstanding smaller bugs/jiras that we can reasonably finish this week I believe :) I volunteer to be a release manager for this release. Cheers, Gyula