Hi Devs!

Based on the previously agreed release schedule for the operator
<https://cwiki.apache.org/confluence/display/FLINK/Release+Schedule+and+Planning>
the
next target release date is Aug 1.  According to the schedule July 11 would
have been Feature Freeze and Jul 18 the time of release cut.

I propose the following timeline based on the current status:

Feature Freeze: July 13 (tomorrow)
Release Branch Cut + RC1: July 20

Based on this we would not merge new feature PRs opened after tomorrow
before the 1.1 release is cut.  There are a few outstanding smaller
bugs/jiras that we can reasonably finish this week I believe :)

I volunteer to be a release manager for this release.

Cheers,
Gyula