Hi community,

It has been three weeks since we cut the release-1.10 branch and kicked off
the release testing phase [1]. Thanks to all the efforts of the community,
46 blocker and 11 critical issues [2] have been resolved during this
period, and now we are left with only 12 blocker issues [3].

If everything goes smoothly, we could possibly resolve all blockers and
produce the first RC in the 3rd week of Jan. Please be prepared for testing
the RC and let us know if there are any questions.

Best,
Gary and Yu

[1] https://s.apache.org/1okuv
[2] https://s.apache.org/gbd0r
[3] https://s.apache.org/euzaj