Hi.

Some of our PPMC members made an offline alignment, and here's what we are
going to do with our following releases.

The release candidate frequency should be about one month.
We will discuss what issues to fix and what features to add one month
before on this mail list.

For example, the sprint from 1st Oct to 31th Oct, we should plan this
version at the beginning of September.
One of the PPMC member will send a sprint kickoff email to the mail list,
and ask everyone (including developers from the community) to add issues
they are going to fix in this version. Then, PPMC member will discuss into
conclusion the final list and make a milestone on GitHub.

Hope this helps the community to know what we are planning to do, and join
on what's most needed.

Wenli