11/09/2019 19:55, Ferruh Yigit:
> There are two constraints for the .02 releases which makes it harder to plan,
> the Christmas/New Year's holidays and Chinese Spring Festival Holiday.
> 
> This years schedule for them is:
> 
> * Christmas/New Year's:
>   25,26 December; 1 January. In practice many people will be on leave on WW52.
> 
> * Chinese Spring Festival Holiday:
>   24-30 January (inclusive).
> 
> 
> According above dates proposed dates are:
> 
> Proposal/V1:          6 December (4 weeks)                            [WW49]
> Integration/Merge/RC1:        10 January (5 weeks including Christmas)        
> [WW2]
> Release:              7 February (4 weeks including Spring Festival)  [WW6]

10 January for integration deadline is short.
And we should give more time after China holiday.
I suggest to shift rc1 and final release dates by one week.