Thank you for your support. Please find the proposed timeline below for 
discussion:

4.16.0.0 release - target for end Q3 2021
(6 weeks) Ongoing - End of August 2021: accept all bugs, issues, improvements 
allowed in LTS [1]
(2 weeks) Mid-September 2021: accept only critical/blocker fixes
(1 week) Stabilise 4.16 branch, accept only blocker issues if any
End of September 2021: Cut 4.16.0.0 RC1 and further RCs if necessary, 
start/conclude vote, and finish release work

[1] https://cwiki.apache.org/confluence/display/CLOUDSTACK/LTS

Any thoughts/objections?


Regards,

Nicolas Vazquez

________________________________

 

From: Nicolas Vazquez
Sent: Wednesday, June 23, 2021 10:32 AM
To: dev@cloudstack.apache.org <dev@cloudstack.apache.org>
Cc: us...@cloudstack.apache.org <us...@cloudstack.apache.org>
Subject: [PROPOSE] RM for 4.16

Dear All,

I’d like to put myself forward as the release manager for 4.16.0.0 and my 
colleagues Suresh Anaparti and Rohit Yadav as the co-RMs.

For 4.16.0.0 my colleague Suresh will assist me during the process for 
reviewing/testing/merging the PRs, others will be welcome to support as well.

I propose we have a window of at least 8 weeks (2 months) to allow community 
and users to test and report issues and aim to cut RC1 in Q3 2021 (September or 
onwards). I'll propose timeline and details by the end of July.

I hope to have your support. Any thoughts, feedback, comments? Thanks.


Regards,

Nicolas Vazquez