Hi all,

with regards to the freeze date, it seems that we'll have to push it back a
bit, again.

I have not had time to do much myself (will rejoin the effort starting from
Monday), but I can see that we have reduced total number of Milestone items
(for both 4.14 and 4.13.1) by 1/3 (we went from ~60 to ~40) - this leaves
us with roughly another **2 weeks** to finish off the remaining milestone
items. Next time I might propose a very "pessimistic" dates, instead of
overly optimistic (that original dates I proposed seem to be), to avoid
postponing the release by this amount of time.

I hope that everyone finds this OK - at the end of the day, WHAT we release
it what's going to be remembered, not WHEN we released it.
As usual, I will follow up here once we are close to the freeze date.

If anyone has any concerns, please let me know.

Thanks,
Andrija


On Wed, 22 Jan 2020 at 15:18, Boris Stoyanov <boris.stoya...@shapeblue.com>
wrote:

> +1, I'd really love to see some of the PRs with the 4.14 milestone in but
> I need more time to test them.
>
> Bobby.
>
> On 22.01.20, 13:22, "Andrija Panic" <andrija.pa...@gmail.com> wrote:
>
>     Hi all,
>
>     I’d like to push back the freeze date for at least a week vs. what's
>     previously proposed since I’ve been contacted by a few people who have
> some
>     PRs they like to get closed off.  If of any interest, I’m away
> 27th-31th
>     January (but will check emails occasionally).
>
>     I'll follow-up here on the freeze date.
>
>     Thanks,
>     Andrija
>
>
>
> boris.stoya...@shapeblue.com
> www.shapeblue.com
> Amadeus House, Floral Street, London  WC2E 9DPUK
> @shapeblue
>
>
>
> On Fri, 20 Dec 2019 at 16:30, Andrija Panic <andrija.pa...@gmail.com>
> wrote:
>
>     > Hi guys
>     >
>     > Sven,
>     > read the original email pls (last part of it) - we will need to fix
> some
>     > bugs, test other people fixes as applicable, etc - "usual" day to dev
>     > stuff.
>     >
>     > Gabriel,
>     >
>     > thx for the help (in advance! ), let's aim to improve the page
> during this
>     > release, I'll surely raise this if/when I see a problem (considering
> this
>     > is my first time but I will also have help from other experienced
> guys as
>     > already explained).
>     >
>     > As for the LTS discussion, I would add that there is an "awful" lot
> of new
>     > stuff planned for this releases, making it a more suitable candidate
> for
>     > LTS then for non-LTS, if that makes sense.
>     >
>     > Anyway, looking forward working with all you guys on this one!
>     >
>     > Best,
>     > Andrija
>     >
>     >
>     >
>     > On Fri, 20 Dec 2019, 12:24 Sven Vogel, <s.vo...@ewerk.com> wrote:
>     >
>     >> @Paul @Gabriel
>     >>
>     >>
>     >>
> https://cwiki.apache.org/confluence/display/CLOUDSTACK/Release+Procedure
>     >>
>     >>
>     >> This seems the link for the release process. I read them. how is it
>     >> possible to engage in this process? I don’t know. Is it useful. I
> would
>     >> come more into and learn it.
>     >>
>     >>
>     >>
>     >>
>     >> Von meinem iPhone gesendet
>     >>
>     >>
>     >> __
>     >>
>     >> Sven Vogel
>     >> Teamlead Platform
>     >>
>     >> EWERK DIGITAL GmbH
>     >> Brühl 24, D-04109 Leipzig
>     >> P +49 341 42649 - 99
>     >> F +49 341 42649 - 98
>     >> s.vo...@ewerk.com
>     >> www.ewerk.com
>     >>
>     >> Geschäftsführer:
>     >> Dr. Erik Wende, Hendrik Schubert, Frank Richter
>     >> Registergericht: Leipzig HRB 9065
>     >>
>     >> Support:
>     >> +49 341 42649 555
>     >>
>     >> Zertifiziert nach:
>     >> ISO/IEC 27001:2013
>     >> DIN EN ISO 9001:2015
>     >> DIN ISO/IEC 20000-1:2011
>     >>
>     >> ISAE 3402 Typ II Assessed
>     >>
>     >> EWERK-Blog<https://blog.ewerk.com/> | LinkedIn<
>     >> https://www.linkedin.com/company/ewerk-group> | Xing<
>     >> https://www.xing.com/company/ewerk> | Twitter<
>     >> https://twitter.com/EWERK_Group> | Facebook<
>     >> https://de-de.facebook.com/EWERK.IT/>
>     >>
>     >> Mit Handelsregistereintragung vom 09.07.2019 ist die EWERK RZ GmbH
> auf
>     >> die EWERK IT GmbH verschmolzen und firmiert nun gemeinsam unter dem
> Namen:
>     >> EWERK DIGITAL GmbH, für weitere Informationen klicken Sie hier<
>     >> https://www.ewerk.com/ewerkdigital>.
>     >>
>     >> Auskünfte und Angebote per Mail sind freibleibend und unverbindlich.
>     >>
>     >> Disclaimer Privacy:
>     >> Der Inhalt dieser E-Mail (einschließlich etwaiger beigefügter
> Dateien)
>     >> ist vertraulich und nur für den Empfänger bestimmt. Sollten Sie
> nicht der
>     >> bestimmungsgemäße Empfänger sein, ist Ihnen jegliche Offenlegung,
>     >> Vervielfältigung, Weitergabe oder Nutzung des Inhalts untersagt.
> Bitte
>     >> informieren Sie in diesem Fall unverzüglich den Absender und
> löschen Sie
>     >> die E-Mail (einschließlich etwaiger beigefügter Dateien) von Ihrem
> System.
>     >> Vielen Dank.
>     >>
>     >> The contents of this e-mail (including any attachments) are
> confidential
>     >> and may be legally privileged. If you are not the intended
> recipient of
>     >> this e-mail, any disclosure, copying, distribution or use of its
> contents
>     >> is strictly prohibited, and you should please notify the sender
> immediately
>     >> and then delete it (including any attachments) from your system.
> Thank you.
>     >>
>     >> Am 20.12.2019 um 12:01 schrieb Gabriel Beims Bräscher <
>     >> gabrasc...@gmail.com>:
>     >>
>     >> Hi Paul, thanks for the clarification.
>     >> First of all, count with me for any help with the 4.14 release
> process :-)
>     >>
>     >> I have no problem with 4.14 becoming the next LTS, having 2 LTS
> releases
>     >> per year sounds good. It is worth to mention that with the past
> releases
>     >> holding +200 commits it was quite a challenge to ensure stability.
> Just
>     >> raising attention to the fact that we might need to support 2 LTS in
>     >> parallel for longer than on prior LTS (not a problem for me). Hope
> that we
>     >> can keep a nice balance between new features and stability.
>     >>
>     >> Additionally, we have some outdated documents regarding the
> releasing
>     >> process and it must be reviewed and updated accordingly. This was a
>     >> problem
>     >> for me when releasing 4.12.
>     >> For the future, I would like to see a discussion around the
> releasing
>     >> process and the pace for future releases. With such discussion
> formalized
>     >> and documented, we can make life easier for RMs and also give a
> better
>     >> perspective of the project status and roadmap to users/developers.
>     >>
>     >> Kind regards,
>     >> Gabriel.
>     >>
>     >> Em qui., 19 de dez. de 2019 às 19:58, Greg Goodrich <
>     >> ggoodr...@ippathways.com> escreveu:
>     >>
>     >> A minor note that those 4.14 dates should all be 2020, not 2019
>     >>
>     >> --
>     >> Greg Goodrich | IP Pathways
>     >> Senior Developer
>     >> 3600 109th Street | Urbandale, IA 50322
>     >> p. 515.422.9346 | e. ggoodr...@ippathways.com<mailto:
> j...@ippathways.com>
>     >>
>     >> On Dec 19, 2019, at 12:30 PM, Paul Angus <paul.an...@shapeblue.com
>     >> <mailto:
>     >> paul.an...@shapeblue.com>> wrote:
>     >>
>     >> I can answer that one...
>     >>
>     >> The 'plan' was always 2 new LTS branches a year - effectively
> summer and
>     >> winter.  Remember at the time, some members of the community were
> going
>     >> for
>     >> a release every month. So the idea was - whatever the branch was the
>     >> current branch at the time that an LTS was due, that branch would
> get some
>     >> 'extra treatment' and be supported for a few years rather than a few
>     >> months.
>     >>
>     >> Very importantly, the post x.x.0 LTS releases were to have no new
> features
>     >> - just bugfixes.  So larger organisations with stricter change
> control,
>     >> their own documentation and their own integrations, could stay on a
>     >> 'supported' branch but still get bug fixes in releases, without
> having to
>     >> worry about, test or document new features constantly.
>     >>
>     >> (I'll hand-wave over the fact that one person's feature is another
>     >> person's improvement, is another person's bugfix)
>     >>
>     >> Yes 4.13 is young (and an LTS) so there will undoubtably a 4.13.1
> with all
>     >> critical/blocker/major bugfixes in it (probably as soon as enough
> people
>     >> have recovered from a 4.14 release cycle) but it can't have any new
>     >> features in it.
>     >>
>     >> So looking forward, if someone wants a 4.15 release in (say) April,
> then
>     >> the 'summer' LTS branch (July/August time) will be 4.16, if not,
> then the
>     >> summer LTS release would be 4.15
>     >>
>     >> I hope that helps 😊
>     >>
>     >>
>     >> Kind regards
>     >>
>     >> Paul.
>     >>
>     >>
>     >> paul.an...@shapeblue.com<mailto:paul.an...@shapeblue.com>
>     >> www.shapeblue.com<http://www.shapeblue.com>
>     >> Amadeus House, Floral Street, London  WC2E 9DPUK
>     >> @shapeblue
>     >>
>     >>
>     >>
>     >>
>     >> -----Original Message-----
>     >> From: Gabriel Beims Bräscher <gabrasc...@gmail.com>
>     >> Sent: 19 December 2019 16:59
>     >> To: dev <dev@cloudstack.apache.org>
>     >> Subject: Re: [PROPOSE] RM for 4.14
>     >>
>     >> Hello Andrija,
>     >>
>     >> That is always good news to have contributors stepping up and
> getting new
>     >> releases done. We definitely need a release (either a major or a
> 4.13.1.0)
>     >> to keep the project traction. However, I would like to understand
> why
>     >> 4.14.0.0 is being considered an LTS release.
>     >> As far as I know, the next major release was supposed to be a
> regular
>     >> (non-LTS) release in the midle of the current LTS and next one LTS.
> Our
>     >> current LTS 4.13.0.0 is young and with still has some room for
> bugfixes.
>     >>
>     >> For reference, here follows the Release Calendar, more details at
> [1].
>     >> 4.9.2.0, LTS, released at 15 December 2016,  EOL 1 July 2018
> 4.9.3.0, LTS,
>     >> released at 11 September 2017,  EOL 1 July 2018 4.11.0.0, LTS,
> released at
>     >> 12 February 2018,  EOL July 2019 4.12.0.0, Regular, released at 4
> April
>     >> 2019, N/A 4.13.0.0, LTS, released at 24 September 2019, Current LTS
>     >> 4.14.0.0, LTS/Regular, planned to 21.Feb 2019+
>     >>
>     >> [1] https://cwiki.apache.org/confluence/display/CLOUDSTACK/LTS
>     >>
>     >> Regards,
>     >> Gabriel.
>     >>
>     >>
>     >> Em qui., 19 de dez. de 2019 às 17:25, Sven Vogel <s.vo...@ewerk.com
> >
>     >> escreveu:
>     >>
>     >> Hi Andrija,
>     >>
>     >> How can I help and engage in this process?
>     >>
>     >> Cheers
>     >>
>     >> Sven
>     >>
>     >>
>     >>
>     >> __
>     >>
>     >> Sven Vogel
>     >> Teamlead Platform
>     >>
>     >> EWERK DIGITAL GmbH
>     >> Brühl 24, D-04109 Leipzig
>     >> P +49 341 42649 - 99
>     >> F +49 341 42649 - 98
>     >> s.vo...@ewerk.com
>     >> www.ewerk.com
>     >>
>     >> Geschäftsführer:
>     >> Dr. Erik Wende, Hendrik Schubert, Frank Richter
>     >> Registergericht: Leipzig HRB 9065
>     >>
>     >> Zertifiziert nach:
>     >> ISO/IEC 27001:2013
>     >> DIN EN ISO 9001:2015
>     >> DIN ISO/IEC 20000-1:2011
>     >>
>     >> EWERK-Blog | LinkedIn | Xing | Twitter | Facebook
>     >>
>     >> Auskünfte und Angebote per Mail sind freibleibend und unverbindlich.
>     >>
>     >> Disclaimer Privacy:
>     >> Der Inhalt dieser E-Mail (einschließlich etwaiger beigefügter
> Dateien)
>     >> ist vertraulich und nur für den Empfänger bestimmt. Sollten Sie
> nicht
>     >> der bestimmungsgemäße Empfänger sein, ist Ihnen jegliche
> Offenlegung,
>     >> Vervielfältigung, Weitergabe oder Nutzung des Inhalts untersagt.
> Bitte
>     >> informieren Sie in diesem Fall unverzüglich den Absender und löschen
>     >> Sie die E-Mail (einschließlich etwaiger beigefügter Dateien) von
> Ihrem
>     >> System.
>     >> Vielen Dank.
>     >>
>     >> The contents of this e-mail (including any attachments) are
>     >> confidential and may be legally privileged. If you are not the
>     >> intended recipient of this e-mail, any disclosure, copying,
>     >> distribution or use of its contents is strictly prohibited, and you
>     >> should please notify the sender immediately and then delete it
> (including
>     >> any attachments) from your system. Thank you.
>     >> Am 19.12.2019 um 17:05 schrieb Andrija Panic <
> andrija.pa...@gmail.com>:
>     >>
>     >> Hi All,
>     >>
>     >> I’d like to put myself forward as release manager for 4.14. The
>     >> 4.14 releases will be the next major version LTS release and will be
>     >> supported for 20 months per the LTS manifesto [2].
>     >>
>     >> I'll have support from Rohit/Daan/Paul during the process and anyone
>     >> else interested is most welcome to join the effort.
>     >>
>     >> The proposed timeline (possibly a bit too ambitious) is as follows:
>     >>
>     >> ######################################
>     >> 24.Jan 2019               -->   Code freeze
>     >> 31.Jan-07.Feb 2019     -->   Cut first RC
>     >> 21.Feb 2019+             -->   Release
>     >> ######################################
>     >>
>     >> As usual, kindly note the following "behaviour" to be in place
>     >> (pretty much copy/paste from the related 4.11 email from Rohit):
>     >>
>     >> ######################################
>     >> 1. After the freeze date (expected 24th Jan) until GA release,
>     >> features will not be allowed and fixes will be only as long as there
>     >> are blocker issues outstanding. Fixes for other issues will be
>     >> individually judged on their merit and risk.
>     >> 2. RM will triage/report critical and blocker bugs for 4.14 and
>     >> encourage people to get them fixed.
>     >> 3. RM will create RCs and start voting once blocker bugs are cleared
>     >> and baseline smoke test results are on par with previous 4.13 smoke
>     >> test
>     >> results
>     >> test results.
>     >> 4. RM will allocate at least a week for branch stabilization and
> testing.
>     >> At the earliest, on 31st January, RM will put 4.14.0.0-rc1 for
>     >> voting
>     >> from
>     >> the 4.14 branch, and master will be open to accepting new features.
>     >> 5. RM will repeat 2-4 as required. Voting/testing of -rc2, -rc3 and
>     >> so
>     >> on,
>     >> will be created as required
>     >> 6. Once vote passes - RM will continue with the release procedures
> [1].
>     >>
>     >> I’d like the community (including myself and colleagues) to:
>     >> - Up to 24th January, community members try to review, test and
>     >> merge as many fixes as possible, being super-diligent to not
>     >> de-stabilize the master branch.
>     >> - Engage with gatekeepers to get your PRs reviewed, tested and
>     >> merged (currently myself, Rohit, Daan and Paul, others are welcome
>     >> to engage as well). Do not merge the PRs
>     >> - A pull request may be reverted where the author(s) are not
>     >> responding and authors may be asked to re-submit their changes after
>     >> taking suitable remedies.
>     >>
>     >> [1]
>     >>
> https://cwiki.apache.org/confluence/display/CLOUDSTACK/Release+Procedu
>     >> re
>     >> [2] https://cwiki.apache.org/confluence/display/CLOUDSTACK/LTS
>     >> ######################################
>     >> --
>     >>
>     >>
>     >> Andrija Panić
>     >>
>     >>
>     >>
>     >>
>
>     --
>
>     Andrija Panić
>
>
>

-- 

Andrija Panić

Reply via email to