When  you say release schedule shift, does it mean 4.5 release target is moved 
from Oct '14 to a forward date?

Thanks & Regards,
Ritu S.

-----Original Message-----
From: Daan Hoogland [mailto:daan.hoogl...@gmail.com] 
Sent: Monday, May 26, 2014 5:26 AM
To: dev
Subject: [ACS45][ACS50][PROPOSAL] move forward feature freeze

LS,

When I seeing once again our release schedule shift, I think we have no option 
but to move feature freeze for the next release forward.
This is the only way it seems we can reduce the complexity of the total sum of 
changes. Therefore it is the only way we can prevent lapsing even more in time 
without risking reduced quality of our next release.
So I propose to move feature freeze forward by a month to be at the 19th of 
June (instead of July). I don't think we need to strictly move code freeze 
forward as well but vigilance onto added features will be necessary.

--
Daan