looks like a plan, Animesh

On Sat, Oct 12, 2013 at 3:14 AM, Animesh Chaturvedi
<animesh.chaturv...@citrix.com> wrote:
> Folks
>
> I would like to propose the following schedule for 4.3. Please note that I 
> have pushed it out by 1 week for multiple reasons
> 1) Until end of September our focus was on 4.2 and master needs to be 
> stabilized before feature freeze
> 2) The original RC was scheduled closer to Christmas and it seemed 
> impractical because of holidays  so I moved it out to January 10th giving us 
> some extra time for RC preparation
>
> I would like to also propose that we target 1/31 as our GA date.
>
> 4.3 is expected to be a much smaller release compared to 4.2 and the focus is 
> to reduce our technical debt. We have  600+ unresolved issues out of which 
> 400 are unassigned
>
>
> =================================
>  4.3 detailed schedule proposal:
>  ================================
>
>
>  2013-11-08
>    Feature Freeze
>    All new feature need to have been merged into master by this date.
>    Release branch will be cut on this date.
>    Jenkins updated to include new release branch builds.
>
>  2013-11-09 through 2013-12-06
>    Testing/Bug Fixes (testing against jenkins artifacts)
>    Documentation Finalization
>
>  2013-12-06
>    Docs Freeze (except release notes and translations)
>    Release Branch moves to limited updates only (only commits allowed  in 
> would be release blockers fixes, translation updates, etc...)
>
>  2013-12-07 through 2014-01-10
>    Translation Development and Integration (should be ongoing, but  focused 
> effort)
>    Final regression testing / bug fixes / doc fixes
>
>  2013-01-10
>    4.3.0-RC1 is created, and project level VOTE is called
>
>  2013-01-31
>    4.3.0 is released