looks like a plan, Animesh
On Sat, Oct 12, 2013 at 3:14 AM, Animesh Chaturvedi <animesh.chaturv...@citrix.com> wrote: > Folks > > I would like to propose the following schedule for 4.3. Please note that I > have pushed it out by 1 week for multiple reasons > 1) Until end of September our focus was on 4.2 and master needs to be > stabilized before feature freeze > 2) The original RC was scheduled closer to Christmas and it seemed > impractical because of holidays so I moved it out to January 10th giving us > some extra time for RC preparation > > I would like to also propose that we target 1/31 as our GA date. > > 4.3 is expected to be a much smaller release compared to 4.2 and the focus is > to reduce our technical debt. We have 600+ unresolved issues out of which > 400 are unassigned > > > ================================= > 4.3 detailed schedule proposal: > ================================ > > > 2013-11-08 > Feature Freeze > All new feature need to have been merged into master by this date. > Release branch will be cut on this date. > Jenkins updated to include new release branch builds. > > 2013-11-09 through 2013-12-06 > Testing/Bug Fixes (testing against jenkins artifacts) > Documentation Finalization > > 2013-12-06 > Docs Freeze (except release notes and translations) > Release Branch moves to limited updates only (only commits allowed in > would be release blockers fixes, translation updates, etc...) > > 2013-12-07 through 2014-01-10 > Translation Development and Integration (should be ongoing, but focused > effort) > Final regression testing / bug fixes / doc fixes > > 2013-01-10 > 4.3.0-RC1 is created, and project level VOTE is called > > 2013-01-31 > 4.3.0 is released