All,

Since we have taken an eight (8) week delay completing the 4.1.0 release, I 
would like propose that we re-evaluate the timelines for the 4.2.0 release.  
When the schedule was originally conceived, it was intended that the project 
would have eight (8) weeks to focus exclusively on 4.2.0 development.  
Unfortunately, this delay has created an unfortunate conflict between squashing 
4.1.0 bugs and completing 4.2.0 features.  I propose that we acknowledge this 
schedule impact, and push back the 4.2.0 feature freeze date by eight (8) weeks 
to 2 August 2013.  This delay will give the project time to properly review 
merges and address issues holistically, and, hopefully, relieve a good bit of 
the stress incurred by the simultaneous 4.1.0 and 4.2.0 activities.  

Thanks,
-John