On Wed, 2011-01-19 at 10:29 -0600, Jonathan Ellis wrote: > On Tue, Jan 18, 2011 at 12:36 PM, Eric Evans <eev...@rackspace.com> wrote: > > The discussion seems to be petering out and I wonder if that means folks > > are still trying to wrap their heads around everything, or if we have > > consensus. > > > > If we're in agreement on 4 months between releases, and feature-freezing > > branches in the run-up, then that would leave us with say 7 weeks (give > > or take) to land everything in trunk that we expect in the next release > > (and I would think that at this point we'd at least have a good idea > > what that'd be). > > Sounds good. > > I've assigned to the Riptano/Datastax team the issues we can get to in
OK, then I'm going to assume we have consensus on this. So again, we released on Jan 9th, 4 months (nominally) would give us a release date of May 9th. We need a few weeks for testing and bug fixing, say time enough for a couple beta iterations, so let's set a tentative date of April 9 to branch, (just under 7 weeks from now). As of right now I see 71 issues marked 0.8. I haven't been through all of them, some are trivial or have patches attached, but some are no doubt unrealistic considering the time-line. For any issues you're championing, please take some time over the next couple of weeks to make sure the ones marked fixfor-0.8 match what you can accomplish before we branch. Is that reasonable to everyone? -- Eric Evans eev...@rackspace.com