The release branch was cut. Before yhe weekend, I was working on getting
the non-portable Dataflow Java worker built and available before producing
the RC1. The actual building bit doesn't take that long, but there's a
bunch of additional validation that goes along with it.

The current target date for 2.50.0 is September 13th, but ultimately it's
as soon as we have a validated and voted on RC.

On Mon, Aug 14, 2023, 3:43 AM Hong Liang <hlteo...@gmail.com> wrote:

> Thanks for driving this Robert!
>
> It seems the two PRs specified have been merged. A little new to Beam, do
> we have an expected release date for the 2.50 release?
>
> Best,
> Hong
>
> On Thu, Aug 10, 2023 at 3:08 AM Robert Burke <lostl...@apache.org> wrote:
>
>> I'm in the process of producing the Cut branch, but due to various delays
>> on my part, it will not be cut today.
>>
>> There are two outstanding PRs blocking the cut,
>> https://github.com/apache/beam/pull/27947 and
>> https://github.com/apache/beam/pull/27939, but once those are in, I'll
>> proceed. Remaining new issues will be cherry picked as required.
>>
>> Thanks
>> Robert Burke
>> Beam 2.50.0 Release Manager
>>
>> On 2023/07/26 15:49:37 Robert Burke wrote:
>> > Hey Beam community,
>> >
>> > The next release (2.50.0) branch cut is scheduled on August 9th, 2023,
>> > according to
>> > the release calendar [1].
>> >
>> > I volunteer to perform this release. My plan is to cut the branch on
>> that
>> > date, and cherrypick release-blocking fixes afterwards, if any.
>> >
>> > Please help me make sure the release goes smoothly by:
>> > - Making sure that any unresolved release blocking issues for 2.50.0
>> should
>> > have their "Milestone" marked as "2.50.0 Release" as soon as possible.
>> > - Reviewing the current release blockers [2] and remove the Milestone if
>> > they don't meet the criteria at [3].
>> >
>> > Let me know if you have any comments/objections/questions.
>> >
>> > Thanks,
>> >
>> > Robert Burke (he/him)
>> > Beam Go Busybody
>> >
>> > [1]
>> >
>> https://calendar.google.com/calendar/embed?src=0p73sl034k80oob7seouanigd0%40group.calendar.google.com
>> > [2] https://github.com/apache/beam/milestone/14
>> > [3] https://beam.apache.org/contribute/release-blocking/
>> >
>>
>

Reply via email to