Stefan Bodewig wrote:

On Mon, 19 Jan 2004, Antoine Lévy-Lambert <[EMAIL PROTECTED]>
wrote:



Is it OK to delay 1.6.1 by a week, putting :
1.6.1 beta on Thursday, Jan 29 th
1.6.1 final on Thursday, Feb 12th



You have my +1 for delaying 1.6.1 to get the bugs fixed.

One more thing on the release process.  Even if we put a planned date
into the release plan that gets accepted, we still need to have a
formal vote on the final release.  I.e. what you outline above means
that you are going to build a distribution and start a vote thread
mid-February and after it has been approved by the PMC, it becomes the
1.6.1 release.

We really need a formal vote on the distribution deliverable.

Stefan





Hi Stefan,

fine, I will remember to organize a new vote before the release itself.

Cheers,

Antoine


--------------------------------------------------------------------- To unsubscribe, e-mail: [EMAIL PROTECTED] For additional commands, e-mail: [EMAIL PROTECTED]



Reply via email to