The standing schedule for cutting train-64 is week of Monday 13th, which
of course is the week of the all-hands in London and hence unlikely to
happen in practice.
Given that we're looking at a bit of extra deploy wrangling in order to
ship the signin confirmation feature, I propose that we make train-64
and train-65 into three-week cycles, with dates like this:
Week of 20th June: Cut train-64
Week of 27th June: Deploy train-64 to prod
Week of 4th July: Further deploys and QA of sign-in confirmation
Week of 11th July: Cut train-65
That will put us back on our regular schedule for the first full train
of Q3.