Folks 

As we are approaching 4.1 code freeze, we should clarify the process on 
features that are not complete yet but a sub set of functionality that is 
useful is complete. Jira supports sub-tasks and we have used it for few longer 
and complex features like IPv6 and seems an obvious choice.

I have following questions:
1) Parent Task 'Fix Version' :  Should this field continue to reflect the 
release it was originally targeted like 4.1 or it should reflect the 'Fix 
release' of the most recent sub-task that is in progress or  to 'Future'?
2) Parent Task 'Status' : If few sub-tasks are 'In Progress' should parent 
status be 'In Progress' too? Or it should be left at 'Open' I don't think 
parent task automatically track sub-task status

We also need to remember to include sub-task in the report of issues for a 
release. 

Thanks
Animesh





Reply via email to