Folks As we are approaching 4.1 code freeze, we should clarify the process on features that are not complete yet but a sub set of functionality that is useful is complete. Jira supports sub-tasks and we have used it for few longer and complex features like IPv6 and seems an obvious choice.
I have following questions: 1) Parent Task 'Fix Version' : Should this field continue to reflect the release it was originally targeted like 4.1 or it should reflect the 'Fix release' of the most recent sub-task that is in progress or to 'Future'? 2) Parent Task 'Status' : If few sub-tasks are 'In Progress' should parent status be 'In Progress' too? Or it should be left at 'Open' I don't think parent task automatically track sub-task status We also need to remember to include sub-task in the report of issues for a release. Thanks Animesh