Paul Hanson schrieb:
> Currently we have an IBM TS3200 working very well over fibre channel and
> has two Ultrium 4 tape units. If I set concurrency to two (2) then both
> tape units can work fine. However, if only one tape unit is in operation
> and two jobs start for the SAME tape pool, then the jobs are interlaced
> and I would prefer the jobs to be ran sequentially.
> 
>  
> 
> What options do I have for controlling concurrency to get the best from
> the two tape unit library??

feature request: "Maximum Concurrent Jobs" for drives when used with
changer
http://article.gmane.org/gmane.comp.sysutils.backup.bacula.devel/13164/

You can use different priorities.

Ralf

------------------------------------------------------------------------------
_______________________________________________
Bacula-users mailing list
Bacula-users@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/bacula-users

Reply via email to