On Jan 22, 2008 2:26 PM, Bill Szkotnicki <[EMAIL PROTECTED]> wrote:

> I have another question about the timing of things.
> If a client job is scheduled for 9AM one day and the client is not there
> at 9AM ( i.e. a notebook )
> And then it shows up later ( say noon )
> When will the director decide to run the job?
> Is there a periodic attempt to contact the client?
> Is there a relevant section in the documentation?
>


The job should  cancel after the max wait time for the job has elapsed.

See
*Max Wait Time

in  the job resource

John
*
-------------------------------------------------------------------------