Hi all,

Here's a quicky I couldn't find in the archives...  I was looking at  
both "Max Wait Time" and "Incremental Max Wait Time".  The idea being  
that I may want to set an overall max wait and then have a shorter  
wait time on my incrementals.

But this part of the manual has me confused as to which takes  
precedence:

----
Incremental Max Wait Time = <time>
The time specifies the maximum allowed time that an Incremental  
backup job may block waiting for a resource (such as waiting for a  
tape to be mounted, or waiting for the storage or file daemons to  
perform their duties), counted from the when the job starts, (not  
necessarily the same as when the job was scheduled). Please note that  
if there is a Max Wait Time it may also be applied to the job.
----

So if my "Max Wait Time" is set to 3 days or so and my "Incremental  
Max Wait Time" is set to say, 6 hours, which one would apply to an  
Incremental job that has been waiting on a tape?

Thanks,

Charles

___
Charles Sprickman
NetEng/SysAdmin
Bway.net - New York's Best Internet - www.bway.net
[EMAIL PROTECTED] - 212.655.9344


-------------------------------------------------------------------------
This SF.net email is sponsored by: Splunk Inc.
Still grepping through log files to find problems?  Stop.
Now Search log events and configuration files using AJAX and a browser.
Download your FREE copy of Splunk now >>  http://get.splunk.com/
_______________________________________________
Bacula-users mailing list
Bacula-users@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/bacula-users

Reply via email to