I have a schedule set up for several jobs to start at staggered times. I am about 15 tapes and three weeks into a backup set on a 4 drive, 60 slot autochanger. I am running CVS as of a couple of days ago.
A few days ago I changed the schedule so that a job, call it B, that normally started later in the process now starts first. Before the schedule change, job A would take tape drive 0, and job B would take tape drive 1. After the schedule change, B now takes tape drive 0. When A starts it pends because it wants to load its tape into drive 0. The only way around this is to intervene and unload the B tape and load the A tape. Why is this happening, and what is the best way to repair this? I figure it is something at the Volume level, but I've not yet found it. I would expect that in a multi-drive changer the drives would be used on an as-available basis as they should be expected to be identical, but that is not what is happening now. Is there a way to make that happen? Thanks much, -- Michael ------------------------------------------------------------------------- Using Tomcat but need to do more? Need to support web services, security? Get stuff done quickly with pre-integrated technology to make your job easier Download IBM WebSphere Application Server v.1.0.1 based on Apache Geronimo http://sel.as-us.falkag.net/sel?cmd=lnk&kid=120709&bid=263057&dat=121642 _______________________________________________ Bacula-users mailing list Bacula-users@lists.sourceforge.net https://lists.sourceforge.net/lists/listinfo/bacula-users