so I just had my first, probably not my last case of a subcontractor not starting a project and backing out.
It does screw me with my reputation with the customer, but its what it is, I am lining up a new sub. My contract template has a non start/non complete clause of standard verbiage, the whole thing of basically the sub pays whatever it costs beyond any completed work. Im not going to enforce it in this case, but are these clauses actually enforceable? Like could I go hire somebody else at 3x the cost and bill the old sub? In this case Id doubt even with judement id see any dough, Im just curious if anybody has ever had to enforce this?
-- AF mailing list AF@af.afmug.com http://af.afmug.com/mailman/listinfo/af_af.afmug.com