Two ways that I can think of: 1. Dis-Associate the client/node from the schedule (effects one or more nodes in this schedule) 2. Change the STARTDATE to a date in the future (effects ALL nodes in this schedule)
Peter Hitchman <[EMAIL PROTECTED]> Sent by: "ADSM: Dist Stor Manager" <ADSM-L@VM.MARIST.EDU> 09/02/2005 11:04 AM Please respond to "ADSM: Dist Stor Manager" <ADSM-L@VM.MARIST.EDU> To ADSM-L@VM.MARIST.EDU cc Subject [ADSM-L] Temporary disabling a client scheduled job Hi, Using TSM 5.2. I have a set of client schedules defined, is it possible for any one of them to temporarily be disabled? I could not see anything in the description of the update schedule command to do this. I could of course do a delete to stop a job running, but it would be better if I could just disable it. Regards Pete