Hi,

Both node is in Windows NT - Version 4, Release 1, Level 1.0 .  The client and
server are in the same machine. And the db cache hit pct. is 97.7%.


Regards,
Max Kwong







Gerald Wichmann <[EMAIL PROTECTED]> on 06/07/2002 12:41:18 AM

Please respond to "ADSM: Dist Stor Manager" <[EMAIL PROTECTED]>

To:   [EMAIL PROTECTED]
cc:    (bcc: Max LH KWONG/LCSD/HKSARG)

Subject:  Re: Processing Time for incremental backup



Assuming there is nothing obviously different that might be causing this
such as the 2nd client listed below already having a heavy load on it, or
backing up over an extremely slow connection (modem? Even that probably
wouldn't take 5 hours though!) - you're going to have to do a trace to solve
this one and see why it's taking so long. 5 hours to scan 600k objects is
incredibly slow. The fact that the first client zips along fine more then
likely indicates it's not a problem with the TSM server.

Are you using the latest client level? What client and server level are you
using? What are the platforms on both nodes below? All in all, I'm reaching
here.. do a trace. Call Tivoli support if you need help with doing one.

Regards,

Gerald Wichmann
Senior Systems Development Engineer
Zantaz, Inc.
925.598.3099 (w)

-----Original Message-----
From: Max Kwong [mailto:[EMAIL PROTECTED]]
Sent: Wednesday, June 05, 2002 7:57 PM
To: [EMAIL PROTECTED]
Subject: Processing Time for incremental backup

Hi all,

I've a schedule incemental backup processing time is much more than the
others.
The followings is the details of the schedule result.

Normal Schedule Processing Time: 3 minutes
============================================================================
============
05/25/2002 04:56:57 --- SCHEDULEREC STATUS BEGIN
05/25/2002 04:56:57 Total number of objects inspected:  440,573
05/25/2002 04:56:57 Total number of objects backed up:        0
05/25/2002 04:56:57 Total number of objects updated:          0
05/25/2002 04:56:57 Total number of objects rebound:          0
05/25/2002 04:56:57 Total number of objects deleted:          0
05/25/2002 04:56:57 Total number of objects expired:          0
05/25/2002 04:56:57 Total number of objects failed:           0
05/25/2002 04:56:57 Total number of bytes transferred:        0 Bytes
05/25/2002 04:56:57 Data transfer time:                    0.00 sec
05/25/2002 04:56:57 Network data transfer rate:            0.00 KB/sec
05/25/2002 04:56:57 Aggregate data transfer rate:          0.00 KB/sec
05/25/2002 04:56:58 Objects compressed by:                    0%
05/25/2002 04:56:58 Elapsed processing time:           00:03:46
05/25/2002 04:56:58 --- SCHEDULEREC STATUS END
05/25/2002 04:56:58 --- SCHEDULEREC OBJECT END MAP_INCR_BACKUP 05/25/2002
04:30:00
05/25/2002 04:56:58 Scheduled event 'MAP_INCR_BACKUP' completed
successfully.
05/25/2002 04:56:58 Sending results for scheduled event 'MAP_INCR_BACKUP'.
05/25/2002 04:56:58 Results sent to server for scheduled event
'MAP_INCR_BACKUP'.

Problem Schedule Processing Time: 5 Hrs
============================================================================
============
05/31/2002 03:11:31 ANS1898I ***** Processed   682,000 files *****
05/31/2002 03:11:32 --- SCHEDULEREC STATUS BEGIN
05/31/2002 03:11:32 Total number of objects inspected:  682,460
05/31/2002 03:11:32 Total number of objects backed up:        2
05/31/2002 03:11:32 Total number of objects updated:          0
05/31/2002 03:11:32 Total number of objects rebound:          0
05/31/2002 03:11:32 Total number of objects deleted:          0
05/31/2002 03:11:32 Total number of objects expired:          0
05/31/2002 03:11:32 Total number of objects failed:           0
05/31/2002 03:11:32 Total number of bytes transferred:     2.20 KB
05/31/2002 03:11:32 Data transfer time:                    0.00 sec
05/31/2002 03:11:32 Network data transfer rate:            0.00 KB/sec
05/31/2002 03:11:32 Aggregate data transfer rate:          0.00 KB/sec
05/31/2002 03:11:32 Objects compressed by:                   42%
05/31/2002 03:11:32 Elapsed processing time:           05:26:47
05/31/2002 03:11:32 --- SCHEDULEREC STATUS END
05/31/2002 03:11:32 --- SCHEDULEREC OBJECT END MF1_INCR_BACKUP 05/30/2002
21:25:00
05/31/2002 03:11:32 Scheduled event 'MF1_INCR_BACKUP' completed
successfully.
05/31/2002 03:11:32 Sending results for scheduled event 'MF1_INCR_BACKUP'.
05/31/2002 03:11:32 Results sent to server for scheduled event
'MF1_INCR_BACKUP'.

Two backup job using same policy domain. How can l solve this problem?

Regards,
Max

Reply via email to